Swimming pool is back in operation!!
Well done, all concerned!!
It appears that the reopening of the swimming pool was short lived joy.
Cleaning of the holding tanks took place yesterday and today (4th and 5th June 2008) and the pool is being filled with filtered water from the main rather than from the hydrant.
Chlorine and clearing agents are expected to be delivered today and deposited into the pump. Management explained that it would take a day of circulation for the chlorine and clearing agents to improve the water quality.
Let’s hope that the pool would be ready for the kids to enjoy, at least for the last weekend of the school holidays.
Below is an email from the developer.
-----Original Message-----
From: CCH@shcsb.com.my [mailto:CCH@shcsb.com.my]
Sent: Thursday, 5 June, 2008 4:52 PM
To: MAM@shcsb.com.my
Subject: Re: Fwd: Pool
I was informed that the Main Contractor will reimburse or replace the material used by the Contractor directly to FMC.
Since the Main Contractor is unable to treat the water to the required water quality, the Developer is engaging a swimming pool maintenance contractor to treat the pool before handing over the pool to FMC.
We target to achieve the required water quality over the weekend.
As for the granite arch, we will engage a granite specialist to look into solving the problem.
Thank you.
Regards,
CCH
No comments:
Post a Comment